Amsterdam Road Closure
General Drive to Morris Road 
No Thru Traffic
Beginning - June 1, 2020
until further notice

Learn More

Fort Wright - Amsterdam Road Project Updates
See Latest Updates

The City of Fort Wright has contracted with Ford Development for the reconstruction of Amsterdam Road between General Drive and Redwood Drive. In addition to widening the existing pavement and adding curb and gutter, the project will include storm sewer improvements, and the addition of a sidewalk along the north side of the road. The project will be broken up into two phases with approximate schedules outlined as follows:

 

Phase 1General Drive to Morris Road. June 2020 – April 2021

This will consist of the construction of a retaining wall along the south side of the road, pavement replacement, storm sewer improvements, and sidewalk construction.

Phase 2Morris Road to Redwood Drive – April 2021 – October 2021

This will consist of pavement replacement, storm sewer improvements, and sidewalk construction.

During construction, Amsterdam Road will be closed to through traffic, with detour signs at Amsterdam Road & Sleepy Hollow Road, and at Amsterdam Road & Bromley Crescent Springs Road directing traffic along Sleepy Hollow, Route 8 and Bromley-Crescent Springs Road as a detour. 

Additionally, during Phase 1 the intersection of General Drive and Amsterdam Road will be closed to traffic; and during Phase 2 the intersection of Fort Henry Drive and Amsterdam Road will be closed to traffic. 

Local traffic will be maintained for residents of the area. All others are advised to seek alternate routes away from this area between June 2020 and October 2021. Please see the attached "Detour Map" by clicking here.

We encourage you to connect with us on social media, and by visiting us at www.fortwright.com to sign up to receive email news and event updates.